Published Date: Feb 24th, 2025
Work will start Spring 2025 revamping Dunfermline Skatepark.
The current skatepark in the Public Park is more than 20 years old and is nearing the end of its lifespan. With the city’s population steadily growing, a modern, fit-for-purpose facility is needed.
Dunfermline Skatepark before works start
The Dunfermline Regeneration Trust have been the driving force behind this project, leading on the design and consultation process. Plans include a phased approach:
Phase one: Spring 2025 to Summer 2025 - Budget £300,000+
Bendcrete Skateparks will be upgrading the existing skatepark, developing a new facility covering approximately 1,000 square meters on the current footprint. This will offer a fresh and exciting space for skaters of all ages and abilities.
The Dunfermline Regeneration Trust have successfully fundraised over £300,000, including contributions from:
- Avondale Environmental £25,000
- Carnegie Trust £10,000
- Cooperative Community Fund £3,600
- Fife Council £181,765
- Fife Environment Trust £30,000
- Garfield Weston £20,000
- sportscotland £50,000
Design of Dunfermline Skatepark - phase one
With 26 features, the new design includes:
- bowl
- street area with bank ledges, bank hips and grind rail
- beginner's spine with quarterpipe, spine ramp and pump bump
- lower quarterpipe
- flat bank
Phase two: Plans are being developed for a second phase to the skatepark, we’ll update you when more is known.