South & West Fife

Details of works planned for the South & West Fife area in 2024/25 are included below.

Key to progress indicators:

Works still to commence onsite Planned
Works in progress Started
Construction works complete Complete
Construction works postponed Postponed

Road improvements planned for 2024/25

WardTown Location (Click for map)BudgetProgress
1 Saline C51 (A823 to U006) £183,000 Complete
1 Rural A907 Ph1 - Bogside Gateway to West of Gallows Loan £501,000 Complete
1 Rural A907 Ph2 - Rintoul Place, Blairhall to Porterfield, Comrie £431,000 Complete
1 Kincardine Walker Street £51,500 Planned
6 Rural C67 Masterton Road £133,000 Complete
6 Dalgety Bay Lethamhill Roundabout - Roundabout and approaches £81,000 Planned
6 Dalgety Bay St Davids Roundabout - Roundabout and approaches £58,000 Planned

Footway improvements planned for 2024/25

WardTown Location (Click for map)BudgetProgress
  Rosyth Hilton Road To footpath at west of P.O. £59,500 Planned
1 Oakley Sir George Bruce Road Ph 2 £30,000 Complete
6 Inverkeithing Railway Station Access Footpath East side of Boreland Road £23,000 Planned
6 Dalgety Bay Lade Braes Phase 2 of 3 (Lade Green to termination at cul de sac at house 46 - south side) £10,000 Planned
6 Dalgety Bay Lade Braes Phase 3 of 3 (Carncraig Place to termination at cul de sac at house 46 - north side) £5,000 Planned
6 Inverkeithing Hillfield Crescent Ph1 - full length east side £60,000 Complete
5 Rosyth Primrose Avenue Ph2 - Booth Avenue to Anderson Lane and Property  107 to 110 ( North side ) £30,000 Planned
6 Inverkeithing Spencerfield Road - Lock-Up area to No 97 (West side only) £25,000 Started

Lighting improvements planned for 2024/25

WardTown Location (Click for map)BudgetProgress
1 Kincardine Phase 4 - Kilbagie Rd & side streets £105,000 Started
1 Culross Low Causeway & West Car Park £132,000 Planned
6 Dalgety Bay Dalgety Gardens, Inchmickery Ave, Inchmickery Road, Path 165/840 £72,000 Started
5 Rosyth Walter Hay Court £120,000 Planned
1 Aberdour Park Lane £4,500 Planned

Traffic Management improvements planned for 2024/25

WardTown Location (Click for map)BudgetProgress
6 & 7 Rural B981 - Inverkeithing to Crossgates £25,000 Planned
6 Inverkeithing Church Street (bus border) £10,000 Planned
6 Aberdour Development site to Aberdour PS/Hawkcraig Rd (shared use path) £50,000 Planned
1 Rural A907 Gowkhall to Lundin Rd £30,000 Planned

Structural Services planned for 2024/25

WardTown Location (Click for map)Budget Progress
    

Planned patching programme for 2024/25

WardTown Location (Click for map)Budget Progress
    

Cycleways programme for 2024/25

WardTown Location (Click for map)BudgetProgress
  Dalgety Bay The Bridge - Harbour Place £40,000 Planned