Details of works planned for the South & West Fife area in 2024/25 are included below.
Key to progress indicators:
Works still to commence onsite | Planned |
---|---|
Works in progress | Started |
Construction works complete | Complete |
Construction works postponed | Postponed |
Road improvements planned for 2024/25
Ward | Town | Location (Click for map) | Budget | Progress |
---|---|---|---|---|
1 | Saline | C51 (A823 to U006) | £183,000 | Complete |
1 | Rural | A907 Ph1 - Bogside Gateway to West of Gallows Loan | £501,000 | Complete |
1 | Rural | A907 Ph2 - Rintoul Place, Blairhall to Porterfield, Comrie | £431,000 | Complete |
1 | Kincardine | Walker Street | £51,500 | Complete |
6 | Rural | C67 Masterton Road | £133,000 | Complete |
Complete 6 | Dalgety Bay | Lethamhill Roundabout - Roundabout and approaches | £81,000 | Planned |
6 | Dalgety Bay | St Davids Roundabout - Roundabout and approaches | £58,000 | Planned |
Footway improvements planned for 2024/25
Ward | Town | Location (Click for map) | Budget | Progress |
---|---|---|---|---|
Rosyth | Hilton Road To footpath at west of P.O. | £59,500 | Planned | |
1 | Oakley | Sir George Bruce Road Ph 2 | £30,000 | Complete |
6 | Inverkeithing | Railway Station Access Footpath East side of Boreland Road | £23,000 | Started |
6 | Dalgety Bay | Lade Braes Phase 2 of 3 (Lade Green to termination at cul de sac at house 46 - south side) | £10,000 | Planned |
6 | Dalgety Bay | Lade Braes Phase 3 of 3 (Carncraig Place to termination at cul de sac at house 46 - north side) | £5,000 | Planned |
6 | Inverkeithing | Hillfield Crescent Ph1 - full length east side | £60,000 | Complete |
5 | Rosyth | Primrose Avenue Ph2 - Booth Avenue to Anderson Lane and Property 107 to 110 ( North side ) | £30,000 | Complete |
6 | Inverkeithing | Spencerfield Road - Lock-Up area to No 97 (West side only) | £25,000 | Complete |
Lighting improvements planned for 2024/25
Ward | Town | Location (Click for map) | Budget | Progress |
---|---|---|---|---|
1 | Kincardine | Phase 4 - Kilbagie Rd & side streets | £105,000 | Complete |
1 | Culross | Low Causeway & West Car Park | £132,000 | Planned |
6 | Dalgety Bay | Dalgety Gardens, Inchmickery Ave, Inchmickery Road, Path 165/840 | £72,000 | Complete |
5 | Rosyth | Walter Hay Court | £120,000 | Planned |
6 | Dalgety Bay | Lade Braes Ph2 & 3 (west side from Carscraig Place south, plus east side to Lade Green east side south to & inc. Lade Green) | £42,000 | Planned |
1 | Aberdour | Park Lane | £4,500 | Planned |
Traffic Management improvements planned for 2024/25
Ward | Town | Location (Click for map) | Budget | Progress |
---|---|---|---|---|
6 & 7 | Rural | B981 - Inverkeithing to Crossgates | £25,000 | Planned |
6 | Inverkeithing | Church Street (bus border) | £10,000 | Planned |
6 | Aberdour | Development site to Aberdour PS/Hawkcraig Rd (shared use path) | £50,000 | Planned |
1 | Rural | A907 Gowkhall to Lundin Rd | £30,000 | Planned |
Thin Carriageway Surfacing Programme for 2024/25
Ward | Town | Location (Click for map) | Budget | Progress |
---|---|---|---|---|
1 | High Valleyfield | Woodhead Street, Preston Street, Valleyfield Avenue, Dunimarle Street, Burns Street, Forth Crescent, Abbey Street, Chapel Street, Chapel Place | Complete | |
1 | Oakley | Sligo Street | Complete | |
5 | Rosyth | Sherbrooke Road, Linton Place | Complete | |
6 | Dalgety Bay | St Bridgets Brae | Complete | |
Planned patching programme for 2024/25
Ward | Town | Location (Click for map) | Budget | Progress |
---|---|---|---|---|
Cycleways programme for 2024/25
Ward | Town | Location (Click for map) | Budget | Progress |
---|---|---|---|---|
Dalgety Bay | The Bridge - Harbour Place | £40,000 | Started | |
Aberdour | NCN improvement & Aberdour Primary SRtS | £70,000 | Started | |
Limekilns | Path Reconstruction / Upgrade (A985 Admiralty Road to Limekilns) | £105,000 | Planned |