Details of works planned for the Kirkcaldy area in 2024/25 are included below.
Key to progress indicators:
Works still to commence onsite | Planned |
---|---|
Works in progress | Started |
Construction works complete | Complete |
Construction works postponed | Postponed |
Road improvements planned for 2024/25
Ward | Town | Location (Click for map) | Budget | Progress |
---|---|---|---|---|
12 | Kirkcaldy | A910 - Nicol Street - Esplanade to Veterinary Surgery | £190,500 | Postponed |
12 | Kirkcaldy | A921 - The Path / Nether Street - High Street to Ravenscraig Roundabout | £342,500 | Complete |
12 | Kirkcaldy | A921 - Rosslyn Street | £391,000 | Complete |
12 | Kirkcaldy | A915 - Randolph Road | £375,500 | Started |
12 | Kirkcaldy | C96 - Hayfield Road | £115,000 | Planned |
10 | Kirkcaldy | Chapel Level Phase 2 - Junction at Fair Isle Road / Robert Adam Drive and W/B to Broom Road R/A ( W/B only ) | £287,500 | Planned |
Footway improvements planned for 2024/25
Ward | Town | Location (Click for map) | Budget | Progress |
---|---|---|---|---|
10 | Kirkcaldy | Greenloanings - Phase 2 | £44,000 | Complete |
12 | Kirkcaldy | Tweed Avenue | £37,500 | Planned |
11 | Kirkcaldy | Bennochy Road - Phase 2 | £87,000 | Planned |
10 | Kirkcaldy | Dunearn Drive - Community Centre to Templehall Café (both sides) | £123,500 | Started |
10 | Kirkcaldy | Barry Road - In front of primary school | £41,000 | Complete |
12 | Kirkcaldy | Beatty Crescent - Macindoe Crescent to Overton Road | £91,000 | Started |
Lighting improvements planned for 2024/25
Ward | Town | Location (Click for map) | Budget | Progress |
---|---|---|---|---|
12 | Kirkcaldy | Tweed Avenue | £24,000 | Planned |
11 | Kirkcaldy | Bennochy Road Ph 2 | £54,000 | Planned |
12 | Kirkcaldy | Millie Street / Junction Road | £29,500 | Planned |
12 | Kirkcaldy | Transportation Car Parks - St Clair Street / Junction Road | £32,500 | Planned |
9 | Kinghorn | Long Craigs Terrace | £42,000 | Planned |
10 | Kirkcaldy | Dunnikier Estate - Braehead Road | £21,000 | Planned |
11 | Kirkcaldy | William Street, Methven Road, James Grove | £87,000 | Planned |
12 | Kirkcaldy | Smeaton Area - Hayfield Rd, Holly Pl, Veronica Cres, Sycamore Ave, Oaktree Sq & Oaktree Court | £123,000 | Planned |
Traffic Management improvements planned for 2024/25
Ward | Town | Location (Click for map) | Budget | Progress |
---|---|---|---|---|
Kirkcaldy | Road Crash Improvements - Bankhead of Piteadie | £3,500 | Planned | |
9 | Burntisland | A921 Aberdour Road (buildout) | £20,000 | Complete |
10 | Kirkcaldy | Blairmore Road - Traffic Calming | £20,000 | Complete |
10 | Kirkcaldy | Broom Gardens near junction with Broom Road | £10,000 | Started |
9 | Kirkcaldy | Balewarie Road west end | £20,000 | Complete |
9 | Kinghorn | A921 Kirkcaldy Road near Croft an Righ | £30,000 | Planned |
12 | Kirkcaldy | Boreland Road | £30,000 | Planned |
Structural Services planned for 2024/25
Ward | Town | Location (Click for map) | Budget | Progress |
---|---|---|---|---|
Planned patching programme for 2024/25
Ward | Town | Location (Click for map) | Budget | Progress |
---|---|---|---|---|
Cycleways programme for 2024/25
Ward | Town | Location (Click for map) | Budget | Progress |
---|---|---|---|---|
9 | Burntisland | Links to Burntisland Rail Station from NCR76 Link East Ph2 & Ph3 | £50,000 | Started |